Ordering & Delivery

Concrete Delivery Interval Calculator

Estimate intervals from load size and placement rate.

Reviewed by Iqbal Hussain, site editor · Last reviewed ·Sources

Concrete Delivery Interval Inputs

Ordering & Delivery

Formula: Interval = load size ÷ placement rate × 60 minutes.

Estimated Result

30 min
Time between trucks
Loads per hour
2.00

How the Concrete Delivery Interval Calculator Works

The Concrete Delivery Interval Calculator sets truck spacing from load size and placement rate.

  1. 1

    Enter load size

    Enter yardage per truck.

  2. 2

    Enter placement rate

    Enter crew or pump rate in yd³ per hour.

  3. 3

    Read the interval

    Read minutes between trucks.

  4. 4

    Send to dispatch

    Give the interval to the plant.

Concrete Delivery Interval Calculator Formula

Delivery interval equals load size ÷ placement rate × 60.

Interval
T (min) = L (yd³) ÷ R (yd³/h) × 60
Trucks per hour
n = R ÷ L
Rate check
R = L × 60 ÷ T

Worked example: 10 yd³ loads at a placement rate of 30 yd³/h need a truck every 20 minutes.

Field tip: Subtract 5 minutes for wash-out and backing. Trucks need time to position behind the pump.

Concrete Delivery Interval Calculator Conversion Table

The table lists minutes between trucks by load size and placement rate.

Rate (yd³/h)Rate (m³/h)8 yd³ loads (min)9 yd³ loads (min)10 yd³ loads (min)
107.6485460
1511.5323640
2015.3242730
3022.9161820
4030.6121415
6045.98910
8061.2678

What is the Concrete Delivery Interval Calculator?

The Concrete Delivery Interval Calculator is a spacing tool that returns the minutes between ready-mix trucks.

Trucks that arrive too fast wait and lose slump. Trucks that arrive too slow leave the crew idle and risk cold joints.

What are the uses of the Concrete Delivery Interval Calculator?

There are 3 pacing uses of the Concrete Delivery Interval Calculator, including pump pours and hand-placed slabs.

  • Pump pours

    Foremen match trucks to pump output.

  • Hand-placed slabs

    Crews pace trucks for wheelbarrow and chute work.

  • Hot-weather pours

    Supervisors cut wait times in heat.

Method, Review & Sources

The Concrete Delivery Interval Calculator runs entirely in your browser. Every result comes from the formula shown above the inputs; nothing is rounded except bag and truck counts, which round up. Results are estimates for planning and ordering, not engineering advice: confirm dimensions on site and follow your plans, local code, and the product label.

Formula and inputs last checked on by Iqbal Hussain. Found an error? Report it.