Concrete Over-Excavation Calculator

Calculate additional volume from enlarged excavation dimensions.

Reviewed by Iqbal Hussain, site editor · Last reviewed ·Sources

Concrete Over-Excavation Inputs

Ordering & Delivery

Formula: Extra = actual (enlarged) volume − design volume.

Estimated Result

0.57 yd³
Additional concrete
Design volume
1.48 yd³
Actual volume
2.05 yd³
Increase
38.4%

How the Concrete Over-Excavation Calculator Works

The Concrete Over-Excavation Calculator finds the extra concrete placed when an excavation exceeds design size.

  1. 1

    Enter design size

    Enter design length, width, and depth.

  2. 2

    Enter actual size

    Measure the dug size.

  3. 3

    Subtract

    Extra volume equals actual minus design.

  4. 4

    Read the extra

    Read extra yardage and cost impact.

Concrete Over-Excavation Calculator Formula

Over-excavation equals actual excavation volume minus design volume.

Design
Vd = L × W × D
Actual
Va = L′ × W′ × D′
Extra
ΔV (yd³) = (Va − Vd) ÷ 27
Extra %
= (Va ÷ Vd − 1) × 100

Worked example: A 100 ft footing designed at 20 in × 10 in but dug 24 in × 12 in places 2.26 yd³ extra, a 44% overrun.

Field tip: Match bucket width to footing width. A 24 in bucket on a 20 in footing costs 20% more concrete.

Concrete Over-Excavation Calculator Conversion Table

The table lists overrun on a 20 in × 10 in (51 × 25 cm) footing per 100 ft (30.5 m).

Dug width (in)Dug depth (in)Actual (yd³)Extra (yd³)Overrun (%)
20105.140.000
22105.660.5110
24106.171.0320
24127.412.2644
30129.264.1280
361412.967.82152

What is the Concrete Over-Excavation Calculator?

The Concrete Over-Excavation Calculator is a variance tool that returns the extra concrete caused by digging beyond design dimensions.

Earth-formed footings fill whatever the excavator digs. Over-digging by 2 in in each direction adds 44% to a 20 in × 10 in footing.

What are the uses of the Concrete Over-Excavation Calculator?

There are 3 variance uses of the Concrete Over-Excavation Calculator, including change orders and crew feedback.

  • Change orders

    Contractors document extra concrete from soft soil removal.

  • Crew feedback

    Supervisors show operators the cost of overdig.

  • Bid contingencies

    Estimators set overdig allowances.

Method, Review & Sources

The Concrete Over-Excavation Calculator runs entirely in your browser. Every result comes from the formula shown above the inputs; nothing is rounded except bag and truck counts, which round up. Results are estimates for planning and ordering, not engineering advice: confirm dimensions on site and follow your plans, local code, and the product label.